Current level ISDC/ 99_RR/ RR vac5a
Ref.: ISDC/WPR-RR vac5a

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 26 APR 2001 24 APR 2001
Ending 09 MAY 2001 07 MAY 2001
Description :
RR vacation 5
Duration :
2w
Resources :
Reiner Rohlfs is implied for 95%
Constraints :
Cannot start before the end of interOSM op_data_1
Long Description :
NOTE:
This WP is part of the very detailed workpackage chain R.Rohlfs asked for. Constraints are therefore mostly manpower driven.
Responsible:
Reiner Rohlfs
Help
/home/pourbaix/astro/pm/pbx/schedule_new/99_RR.ts/rr_24_vac5.wpd
D.Pourbaix