Current level ISDC/ Op/ op procedures
Ref.: ISDC/WPR-op procedures

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 15 MAY 2000 15 MAY 2000
Ending 25 DEC 2000 25 DEC 2000
Description :
Operation procedures v1
Duration :
7m
StartAfter :
01-MAY-2000
Resources :
Nami Mowlavi is implied for 20%
Long Description :
Specification of the operation procedures at ISDC
Writing of the OMP (Operation Management Plan) Appendices
Inputs:
OMP 2.0
Parts of the Interface Control Documents, ICDs
Outputs:
Updated OMP with the appendices written
Operation procedures specified and documented in a first version
Responsible:
Nami Mowlavi