Current level ISDC/ cal/ cal impl
Ref.: ISDC/WPR-cal impl

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 18 SEP 2000 25 SEP 2000
Ending 22 DEC 2003 29 DEC 2003
Description :
Implementation of the calibration archive
Duration :
37m
Resources :
Nicolas Produit is implied for 10%
Constraints :
Cannot start before the end of cal TN24
Long Description :
Implementation of the calibration archive, i.e. archiving calibration data
NOTE:
This WP is planned to go on throughout the mission and is assumed to start with the SPI calibrations in Bruyeres-le-Chatel.
Inputs:
Knowledge of the the calibration data and the calibration archive
Outputs:
Growing calibration archive
Responsible:
Nicolas Produit
Help
/home/pourbaix/astro/pm/pbx/schedule_new/80_cal.ts/70_cal_impl.wpd
D.Pourbaix