Current level ISDC/ sims/ sims ISDC
Ref.: ISDC/WPR-sims ISDC

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 07 SEP 2001 07 SEP 2001
Ending 04 OCT 2001 04 OCT 2001
Description :
ISDC Simulations
Duration :
4w
Resources :
ISDC Team is implied for 85%
Constraints :
Cannot start before the end of interOSM sys_test
Cannot start before the end of sims sys_test
Must be terminated before the start of sims particip
Long Description :
ISDC level simulations in preparations for the INTEGRAL launch and operations
Inputs:
Completely installed and tested ISDC system
Outputs:
Experience for Operations
Responsible:
Nami Mowlavi
Help
/home/pourbaix/astro/pm/pbx/schedule_new/60_sims.ts/60_sims_ISDC.wpd
D.Pourbaix