Current level ISDC/ sims/ sims prep
Ref.: ISDC/WPR-sims prep

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 23 JAN 2001 26 DEC 2000
Ending 30 MAY 2001 02 MAY 2001
Description :
Preparation of Simulations
Duration :
4m
Resources :
Nami Mowlavi is implied for 10%
Constraints :
Cannot start before the end of op procedures
Cannot start before the end of op IT_interact
Must be terminated before the start of sims particip
Long Description :
Prepare the overall simulations leading to launch
Inputs:
tbd
Outputs:
tbd
Responsible:
Nami Mowlavi