Current level ISDC/ isdc_v3/ isdc_v3 accpt_test
Ref.: ISDC/WPR-isdc_v3 accpt_test

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 08 AUG 2001 08 AUG 2001
Ending 04 SEP 2001 04 SEP 2001
Description :
ISDC v3 Acceptance tests
Duration :
4w
StartOn :
ISDC_v3_date-6w-1d
Resources :
Nami Mowlavi is implied for 60%
Constraints :
Cannot start before the end of QLA accpt_test
Long Description :
Test the whole ISDC Version 3 System against the respective parts of the URD
Inputs:
The system tested ISDC Version 3 System consisting of the appropriate documentation and the following subsystems:
Updates of the subsystems of ISDC Version 2 (listed in the description of the respective workpackage for ISDC v1 and ISDC v2)
ISDC subsystems required for the ISDC Version 3 System:
Archive Management tools and Data Distribution s/w
Offline Calibration, Performance and Background Analysis s/w
Outputs:
A formally accepted ISDC Version 3 System, ready to support regular operations
Responsible:
Nami Mowlavi
Help
/home/pourbaix/astro/pm/pbx/schedule_new/43_isdc_v3.ts/85_isdc_v3_accpt_test.wpd
D.Pourbaix