Current level ISDC/ isdc_v3/ isdc_v3 sys_test
Ref.: ISDC/WPR-isdc_v3 sys_test

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 20 FEB 2002 20 FEB 2002
Ending 19 MAR 2002 19 MAR 2002
Description :
ISDC v3 System tests
Duration :
4w
StartOn :
22-MAR-2001
Resources :
Mathias Beck is implied for 60%
Constraints :
Cannot start before the end of isdc_v3 TRR
Long Description :
Test the whole ISDC Version 3 System against the respective parts of the SRD
Inputs:
Updates of the subsystems of ISDC Version 2 (listed in the description of the respective workpackage for ISDC v1 and ISDC v2)
ISDC subsystems required for the ISDC Version 3 System:
Archive Management tools and Data Distribution s/w
Offline Calibration, Performance and Background Analysis s/w
Outputs:
A properly running ISDC Version 3 System
Appropriate documentation
Responsible:
Mathias Beck
Help
/home/pourbaix/astro/pm/pbx/schedule_new/43_isdc_v3.ts/80_isdc_v3_sys_test.wpd
D.Pourbaix