Current level ISDC/ isdc_v2/ isdc_v2 sys_test
Ref.: ISDC/WPR-isdc_v2 sys_test

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 06 JUL 2001 06 JUL 2001
Ending 02 AUG 2001 02 AUG 2001
Description :
ISDC v2 System tests
Duration :
4w
Resources :
Mathias Beck is implied for 60%
Constraints :
Cannot start before the end of isdc_v2 TRR
Long Description :
Test the whole ISDC Version 2 System against the respective parts of the SRD
NOTE:
ISDC v2 comprises fairly independent subsystems that are planned to be tested separately anyway. These tests may therefore mean to rerun the tests performed before consolidation of ISDC v2.
Inputs:
Updates of the subsystems of ISDC Version 1 (listed in the description of the respective workpackage for ISDC v1)
ISDC subsystems required for the ISDC Version 2 System:
INTEGRAL Burst Alert System (IBAS)
Quick Look Analysis (QLA)
Standard Analysis (SA)
Offline Scientific Analysis (OSA) Infrastructure
Outputs:
A properly running ISDC Version 2 System
Appropriate documentation
Responsible:
Mathias Beck