Current level ISDC/ isdc_v1/ isdc_v1 accpt_test
Ref.: ISDC/WPR-isdc_v1 accpt_test

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 09 MAR 2001 09 MAR 2001
Ending 10 APR 2001 10 APR 2001
Description :
ISDC v1 Acceptance tests
Duration :
1m
StartOn :
IPAR2_date-1m-1d
Resources :
Nami Mowlavi is implied for 40%
Constraints :
Cannot start before the end of isdc_v1 FM_tests
Cannot start before the end of op procedures
Long Description :
Test the whole ISDC v1 System against the respective parts of the URD
Inputs:
The system tested ISDC v1 System consisting of the appropriate documentation and the following subsystems:
Data Receipt (DR)
Auxiliary Data Processing (ADP)
Preprocessing (PP)
Data Preparation (DP)
Instrument Configuration Analysis (ICA)
Automatic Calibration Analysis (ACA)
Operation Status Monitoring (OSM)
Alert Management (AM)
Archive: Ingest, Browse, Access
Archive dB: Meta Data Access
and the corresponding pipelines
Outputs:
A formally accepted ISDC Version 1 System ready to support the Payload Calibrations (P/L Cal) and the Ground Segment Integrated Tests (GSIT)
Responsible:
Nami Mowlavi