Current level ISDC/ isdc_v1/ isdc_v1 FM_tests
Ref.: ISDC/WPR-isdc_v1 FM_tests

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 09 FEB 2001 09 FEB 2001
Ending 08 MAR 2001 08 MAR 2001
Description :
ISDC v1 sys_tests with CD-ROM data
Duration :
4w
Resources :
Mathias Beck is implied for 20%
Constraints :
Cannot start before the end of input_cons sys_accpt
Long Description :
Rerun the ISDC v1 system tests using real CD-ROM testdata and write the corresponding reports.
Inputs:
The system tested ISDC Version 1 System consisting of the appropriate documentation and the following subsystems:
Auxiliary Data Processing (ADP)
Data Receipt (DR)
Preprocessing (PP)
Data Preparation (DP)
Instrument Configuration Analysis (ICA)
Automatic Calibration Analysis (ACA)
Operation Status Monitoring (OSM)
Alert Management (AM)
Archive: Ingest, Browse, Access
Archive dB: Meta Data Access
and the corresponding pipelines
Outputs:
A formally accepted ISDC v1 System ready to support the Payload Calibrations (P/L Cal) and the Ground Segment Integrated Tests (GSIT) tested also with officially received test data.
Responsible:
Mathias Beck
Help
/home/pourbaix/astro/pm/pbx/schedule_new/41_isdc_v1.ts/84_isdc_v1_FM_tests.wpd
D.Pourbaix