Current level ISDC/ isdc_v1/ isdc_v1 sys_test
Ref.: ISDC/WPR-isdc_v1 sys_test

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 25 SEP 2000 14 AUG 2000
Ending 06 OCT 2000 25 AUG 2000
Description :
ISDC v1 System tests
Duration :
2w
Priority :
1
StartOn :
25-SEP-2000
Resources :
Mathias Beck is implied for 80%
Constraints :
Cannot start before the end of isdc_v1 test_prep
Cannot start before the end of archingest sys_accpt
Cannot start before the end of input sys_accpt
Long Description :
Test the whole ISDC v1 System against the respective parts of the SRD
Write the required documents (test specs and reports)
Inputs:
ISDC subsystems required for the ISDC Version 1 System:
Observation Simulator
Automated Analysis Infrastructure (AAI) in form of the OPUS pipelines involved in ISDC v1
Data Receipt (DR)
Auxiliary Data Processing (ADP)
Preprocessing (PP)
Data Preparation (DP)
Instrument Configuration Analysis (ICA)
Automatic Calibration Analysis (ACA)
Operation Status Monitoring (OSM)
Alert Management (AM)
Archive: Ingest, Browse, Access
Archive dB: Meta Data Access
and the corresponding pipelines
Outputs:
A formally system tested ISDC v1 System
Appropriate documentation (Test specs and reports)
Responsible:
Mathias Beck