Current level ISDC/ ObsSim/ OSIM distr_infra
Ref.: ISDC/WPR-OSIM distr_infra

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 02 OCT 2000 16 OCT 2000
Ending 01 NOV 2000 15 NOV 2000
Description :
OSIM Distribution Infrastr.
Duration :
1m
StartAfter :
01-OCT-2000
Resources :
Marc Türler is implied for 20%
Constraints :
Cannot start before the end of OSIM stabil
Cannot start before the end of OSIM PIMMS
Cannot start before the end of OSIM UM
Must be terminated before the start of AO
Long Description :
Develop and implement the web based infrastructure for the distribution of the Observation Simulator OSIM
Outputs:
Distribution infrastructure
Responsible:
Marc Türler
Help
/home/pourbaix/astro/pm/pbx/schedule_new/34_ObSim.ts/55_ObsSim_distr.wpd
D.Pourbaix