Current level ISDC/ ObsSim/ OSIM intg
Ref.: ISDC/WPR-OSIM intg

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 03 APR 2000 03 APR 2000
Ending 15 SEP 2000 15 SEP 2000
Description :
OSIM (Sub-) System Integration and Tests
Duration :
24w
Resources :
Adamantia Paizis is implied for 80%
Constraints :
Cannot start before the end of OSIM v1
Must be terminated before the start of AO
Long Description :
Integrate the stabilized s/w of the Observation Simulator (OSIM)
Test the OSIM (it has to meet the plans specified in the ADD)
Write the required documentation.
Inputs:
Unit tested parts of updated Observation Simulator (OSIM) s/w
Outputs:
Integrated and system tested Observation Simulator ready for packaging for the AO distribution
Required documentation
Responsible:
Adamantia Paizis