Current level ISDC/ ObsSim/ OSIM intg_v1
Ref.: ISDC/WPR-OSIM intg_v1

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 31 MAY 1999 31 MAY 1999
Ending 24 MAR 2000 24 MAR 2000
Description :
OSIM v1 Integration and Tests
Duration :
43w
Resources :
Davide Cremonesi is implied for 50%
Peter Kretschmar is implied for 10%
Antony Bird is implied for 40%
Lockley Jon is implied for 70%
Andrew Strong is implied for 10%
Niels Westergaard is implied for 20%
Adamantia Paizis is implied for 40%
Constraints :
Cannot start before the end of OSIM AD/R
Must be terminated before the start of OSIM v1
Percentage:
100%
Long Description :
Integrate the different parts of the Observation Simulator (OSIM) into one whole Simulator to be used at the school "Observing with INTEGRAL"
Develop some test harness and data for the Simulator
Test the OSIM (it has to meet the plans specified in the ADD)
Write the required documentation
NOTE:
This WP is foreseen to start while the last bits of work on the coding WPs are still being performed.
Inputs:
Unit tested parts of the Observation Simulator (OSIM), notably the ISSSW (Instrument Specific Simulator Software)
Outputs:
Integrated and integration tested Observation Simulator
Required documentation
Responsible:
Davide Cremonesi
Help
/home/pourbaix/astro/pm/pbx/schedule_new/34_ObSim.ts/35_ObsSim_intg_v1.wpd
D.Pourbaix