Current level ISDC/ mls_test/ Simulation
Ref.: ISDC/WPR-Simulation

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 12 NOV 2001 12 NOV 2001
Ending 19 APR 2002 19 APR 2002
Description :
Simulations campaign
Duration :
5m
StartOn :
sims_start
Constraints :
Cannot start before the end of IFAR
Must be terminated before the start of Launch
Long Description :
The mission operations are simulated, especially the Launch and Early Orbit Phase (LEOP)
Help
/home/pourbaix/astro/pm/pbx/schedule_new/15_milestones.ts/96_simul.wpd
D.Pourbaix