Current level ISDC/ mls_test/ FAR
Ref.: ISDC/WPR-FAR

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 11 JAN 2002 11 JAN 2002
Ending 11 JAN 2002 11 JAN 2002
Description :
FAR: Final Accpt Review
StartOn :
FAR_date
Long Description :
Although not necessarily linked to FAR, it is planned to take this date for the ISDC demonstration that its s/w is ready to support the simulations and the commissioning phases
Inputs:
ISDC version 1
Payload calib on spacecraft
IGS tests and SVTs ended.
Outputs:
ISDC deliveries for FAR
Help
/home/pourbaix/astro/pm/pbx/schedule_new/15_milestones.ts/94_far.wpd
D.Pourbaix