Current level ISDC/ mls_test/ IFAR
Ref.: ISDC/WPR-IFAR

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 20 AUG 2001 20 AUG 2001
Ending 14 SEP 2001 14 SEP 2001
Description :
IFAR: ISDC Final Accpt Review
Duration :
4w
StartOn :
IFAR_date-4w-1d
Constraints :
Cannot start before the end of GSIT2
Long Description :
ISDC has to demonstrate that it will be ready to support the simulations and the commissioning phases
Outputs:
ISDC deliveries for IFAR
Help
/home/pourbaix/astro/pm/pbx/schedule_new/15_milestones.ts/92_ifar.wpd
D.Pourbaix