Current level ISDC/ mls_test/ GSIT2
Ref.: ISDC/WPR-GSIT2

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 20 AUG 2001 20 AUG 2001
Ending 24 AUG 2001 24 AUG 2001
Description :
Ground Segm. Integr. Tests (GSIT) 2
Duration :
1w
StartOn :
GSIT2_start
Resources :
Mathias Beck is implied for 80%
Jerzy Borkowski is implied for 10%
Nicolas Morisset is implied for 10%
Reiner Rohlfs is implied for 10%
Laurent Lerusse is implied for 10%
Constraints :
Cannot start before the end of GSIT1
Long Description :
Ground Segment Integration Tests (GSIT) Part 2
The whole loop ISOC->MOC->ISDC->ISOC is tested on a high level