Current level ISDC/ mls_test/ GSIT1
Ref.: ISDC/WPR-GSIT1

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 15 MAY 2001 15 MAY 2001
Ending 31 MAY 2001 31 MAY 2001
Description :
Ground Segm. Integr. Tests (GSIT) 1
Duration :
13d
StartOn :
GSIT1_start
Resources :
Mathias Beck is implied for 80%
Jerzy Borkowski is implied for 10%
Nicolas Morisset is implied for 10%
Reiner Rohlfs is implied for 10%
Laurent Lerusse is implied for 10%
Constraints :
Cannot start before the end of I/F tests
Long Description :
Ground Segment Integration Tests (GSIT) Part 1
The whole loop ISOC->MOC->ISDC->ISOC is tested on a high level