Current level ISDC/ mls_test/ IPAR2
Ref.: ISDC/WPR-IPAR2

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 04 APR 2001 09 MAR 2001
Ending 04 APR 2001 09 MAR 2001
Description :
IPAR 2 (ISDC V1)
StartOn :
IPAR2_date
Constraints :
Cannot start before the end of isdc_v1 FM_tests
Must be terminated before the start of GSIT1
Long Description :
ISDC Provisional Acceptance Review Part 2.
ISDC Version 1 is ready (have a look at the A4 page "ISDC Overall Schedule" for version definitions)
ISDC demonstrates its readyness for the Ground Segment Integration Tests (GSIT)
ISDC supports the close-out of the MOC-SGS i/f test.
Outputs:
ISDC deliveries for IPAR 2 (ISDC v1)