Current level ISDC/ mls_test/ DFT2
Ref.: ISDC/WPR-DFT2

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 22 MAY 2000 22 MAY 2000
Ending 07 JUN 2000 07 JUN 2000
Description :
Dataflow test (DFT) Part 2
Duration :
2w
StartOn :
DFT2_start
Resources :
Mathias Beck is implied for 80%
Constraints :
Must be terminated before the start of GSIT1
Percentage:
100%
Long Description :
A second test of the real time telemetry stream from MOC to ISDC. In the process new testdata is expected to be received.