Current level ISDC/ mls_test/ DFT
Ref.: ISDC/WPR-DFT

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 03 APR 2000 03 APR 2000
Ending 07 APR 2000 07 APR 2000
Description :
Dataflow test (DFT)
Duration :
1w
StartOn :
DFT_start
Resources :
Mathias Beck is implied for 80%
Constraints :
Must be terminated before the start of GSIT1
Percentage:
100%
Long Description :
A test of the real time telemetry stream from MOC to ISDC
Help
/home/pourbaix/astro/pm/pbx/schedule_new/15_milestones.ts/42_DFT.wpd
D.Pourbaix