Current level ISDC/ mgt_gen/ CC/ CC IFAR_prep
Ref.: ISDC/WPR-CC IFAR_prep

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 17 JUL 2001 17 JUL 2001
Ending 18 SEP 2001 18 SEP 2001
Description :
Preparation IFAR
Duration :
2m
StartOn :
IFAR_date-2m-2d
Resources :
David Landriu is implied for 5%
Tim Lock is implied for 2%
Bärbel Kretschmar is implied for 2%
Constraints :
Must be terminated before the start of IFAR
Long Description :
Preparation of a package that contains the complete and up-to-date information to be submitted for IFAR. It shall comprise status information and documentation on s/w, testdata, SPRs and SCREWs.
NOTE:
This WP only covers the "bundling" of existing items. Although updates may be suggested, the "up-to-date-responsibility" lies with the custodians of the different items.
Inputs:
Information on which documents and CC items to prepare
Outputs:
Complete package to submit for IFAR
Responsible:
Help
/home/pourbaix/astro/pm/pbx/schedule_new/10_general_mgt.ts/30_CC.ts/45_CC_ifar_prep.wpd
D.Pourbaix