Dates:

CurrentOriginal
Starting 20 JUN 2001 20 JUN 2001
Ending 22 AUG 2001 22 AUG 2001
Description :
Preparation GSIT 2
Duration :
2m
StartOn :
GSIT2_start-2m-2d
Resources :
David Landriu is implied for 10%
Tim Lock is implied for 5%
Bärbel Kretschmar is implied for 5%
Constraints :
Must be terminated before the start of GSIT2
Long Description :
Preparation of a package that contains the complete and up-to-date information to be submitted for GSIT 2. It shall comprise status information and documentation on s/w, testdata, SPRs and SCREWs.
NOTE:
This WP only covers the "bundling" of existing items. Although updates may be suggested, the "up-to-date-responsibility" lies with the custodians of the different items.
Inputs:
Information on which documents and CC items to prepare
Outputs:
Complete package to submit for GSIT 2
Responsible:
Help