Dates:

CurrentOriginal
Starting 01 NOV 2000 01 NOV 2000
Ending 05 FEB 2001 05 FEB 2001
Description :
Preparation IPAR 2
Duration :
3m
StartOn :
IPAR2_date-3m-2d
Resources :
David Landriu is implied for 10%
Tim Lock is implied for 5%
Bärbel Kretschmar is implied for 5%
Constraints :
Must be terminated before the start of IPAR2
Long Description :
Preparation of a package that contains the complete and up-to-date information to be submitted for IPAR 2 (ISDC v1 release). It shall comprise status information and documentation on s/w, testdata, SPRs and SCREWs.
NOTE:
This WP only covers the "bundling" of existing items. Although updates may be suggested, the "up-to-date-responsibility" lies with the custodians of the different items.
Inputs:
Information on which documents and CC items to prepare
Outputs:
Complete package to submit for IPAR 2
Responsible:
Help