Current level
ISDC/
mgt_gen/
CC/
CC IPAR1_prep
Ref.: ISDC/WPR-CC IPAR1_prep
Work Package Report
Post a new report
Dates:
| Current | Original
|
---|
Starting
| 01 NOV 1999
| 01 NOV 1999
|
---|
Ending
| 11 JAN 2000
| 11 JAN 2000
|
---|
- Description :
- Preparation IPAR 1
- Duration :
- 3m
- StartOn :
- IPAR1_date-3m-2d
- Resources :
-
David Landriu
is implied for 10%
-
Tim Lock
is implied for 5%
-
Bärbel Kretschmar
is implied for 5%
- Constraints :
-
Must be terminated before the start of IPAR1
- Percentage:
- 100%
- Long Description :
- Preparation of a package that contains the complete and up-to-date information to be submitted for IPAR 1
(ISDC v1 front end = input pipeline).
It shall comprise status information and documentation on s/w, testdata, SPRs and SCREWs.
-
NOTE:
-
This WP only covers the "bundling" of existing items. Although updates may be suggested,
the "up-to-date-responsibility" lies with the custodians of the different items.
- Inputs:
- Information on which documents and CC items to prepare
- Outputs:
- Complete package to submit for IPAR 1
- Responsible:
-
Help
/home/pourbaix/astro/pm/pbx/schedule_new/10_general_mgt.ts/30_CC.ts/41_CC_ipar1_prep.wpd
D.Pourbaix