Current level ISDC/ mgt_gen/ CC/ CC www_work
Ref.: ISDC/WPR-CC www_work

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 01 AUG 1997 01 AUG 1997
Ending 24 MAR 2003 24 MAR 2003
Description :
Maintain WWW pages
Duration :
64m
Resources :
David Landriu is implied for 10%
Constraints :
Cannot start before the end of CC www_setup
Percentage:
10%
Long Description :
Maintain the web pages on the s/w configuration items, such as the s/w modules, SPRs and SCREWs. Emphasis is to be put on very regular, if not automated, updates of the contents and status of the configuration library, the SPR and the SCREW systems providing requested information to the interested person. In particular, hyperlinks shall create the possibility to assess the available information following different criteria, such as
delivery history
s/w belonging to the same ISDC subsystem (hierarchy)
s/w in the same area (RELEASE, TEST, INTEGRATION)
a single cc s/w item (links between delivered code, delivery note, SPRs, SCREWs, versions, etc).
Furthermore, improvements shall be made of the procedures and mechanisms which provide and set up these web pages
NOTE:
This WP shall continue as long as s/w is maintained at ISDC
Inputs:
Existing web pages
Outputs:
Up-to-date web pages
Responsible:
David Landriu
Help
/home/pourbaix/astro/pm/pbx/schedule_new/10_general_mgt.ts/30_CC.ts/26_CC_www_work.wpd
D.Pourbaix