Dates:

CurrentOriginal
Starting 01 SEP 1999 01 SEP 1999
Ending 11 MAR 2003 11 MAR 2003
Description :
Maintain the Change control systems
Duration :
40m
Resources :
David Landriu is implied for 10%
Constraints :
Cannot start before the end of CC change_setup
Long Description :
Perform the day-to-day work linked to the systems requesting changes in the configuration controlled items (Software Problem Report, SPR, and Software Change Requests and Extra Wishes, SCREW, systems). This includes:
Accepting SPRs and SCREWs
Assessing every single one of them, linking them to the CC item and passing them on to the responsible person(s)
Keeping track of their status on the basis of information provided by third parties
Improve the procedures and mechanisms in this area of work
NOTE:
This WP shall be ongoing as long as s/w is maintained at ISDC
Inputs:
SPR and SCREW systems
Outputs:
Up-to-date SPR and SCREW systems and content
Responsible:
David Landriu