Work Package Report
Post a new report
Dates:
| Current | Original
|
---|
Starting
| 02 JUN 1997
| 02 JUN 1997
|
---|
Ending
| 31 DEC 1999
| 31 DEC 1999
|
---|
- Description :
- Setup of change control systems
- Duration :
- 135w
- Resources :
-
David Landriu
is implied for 10%
- Percentage:
- 100%
- Long Description :
- Setting up a Software Problem Reporting/fixing (SPR) mechanism
-
Setting up a Software Change Request and Extra Wishes (SCREW) submission system
- Outputs:
- SPR and SCREW systems
- Responsible:
-
David Landriu