Current level ISDC/ mgt_gen/ GS test prep
Ref.: ISDC/WPR-GS test prep

Work Package Report


Post a new report

Dates:

CurrentOriginal
Starting 13 JAN 2000 13 JAN 2000
Ending 17 OCT 2001 17 OCT 2001
Description :
Preparation of GS level tests
Duration :
20m
Resources :
Mathias Beck is implied for 2%
Tim Lock is implied for 2%
Constraints :
Must be terminated before the start of Launch
Long Description :
Participate in the preparations for the GS level tests.
This implies in particular taking part in the ITT meetings and evaluation of test procedures and schedules.
Responsible:
Help
/home/pourbaix/astro/pm/pbx/schedule_new/10_general_mgt.ts/55_GS_test_prep.wpd
D.Pourbaix