Current level ISDC/ ISSW/ OMC ISSW

Schedule Report


Dates:

CurrentOriginal
Starting 14 JUL 1997 14 JUL 1997
Ending 31 MAY 2001 31 MAY 2001
Percentage:
30%
Long Description :
Development of the OMC ISSW (Instrument Specific Software). The workpackages at include:
Writing of necessary I/F documents and (development) plans
Writing (or taking part in the writing) of instrument specific SRD (Software Requirement Document) and ADDs (Architectural Design Document)
Coding and unit testing of OMC specific executables
Writing the required documentation
Support in the integration phase at ISDC
Maintenance of the s/w (for better traceability of the development those WPs have been moved to the maintenance part)
Responsible:
The Gantt chart at this level

Gantt chart
Link to the equivalent Encapsulated PostScript file

Help
/home/pourbaix/astro/pm/pbx/schedule_new/50_issw.ts/96_omc_issw.ts/summary.rpt


D.Pourbaix