Current level ISDC/ ISSW/ JEM-X ISSW

Schedule Report


Dates:

CurrentOriginal
Starting 14 JUL 1997 14 JUL 1997
Ending 31 MAY 2001 31 MAY 2001
Percentage:
35%
Long Description :
Development of the JEM-X ISSW (Instrument Specific Software). The workpackages at include:
Writing of necessary I/F documents and (development) plans
Writing (or taking part in the writing) of instrument specific SRD (Software Requirement Document) and ADDs (Architectural Design Document)
Coding and unit testing of JEM-X specific executables
Writing the required documentation
Support in the integration phase at ISDC
Maintenance of the s/w (for better traceability of the development, this WPs have been moved to the Maintenance part)
Responsible:
The Gantt chart at this level

Gantt chart
Link to the equivalent Encapsulated PostScript file

Help
/home/pourbaix/astro/pm/pbx/schedule_new/50_issw.ts/94_jemx_issw.ts/summary.rpt


D.Pourbaix