Current level ISDC/ isdc_v3

Schedule Report


Dates:

CurrentOriginal
Starting 12 JUN 2000 12 MAY 2000
Ending 19 MAR 2002 19 MAR 2002
Description :
ISDC v3 development
Long Description :
Develop, coding, unit testing and documenting the s/w needed for ISDC v3.
Release of this s/w is currently planned for the beginning of the pre-launch simulation phase.
Responsible:
Roland Walter
The Gantt chart at this level

Gantt chart
Link to the equivalent Encapsulated PostScript file

Help
/home/pourbaix/astro/pm/pbx/schedule_new/43_isdc_v3.ts/summary.rpt


D.Pourbaix